Site manager's progress report

Structural steel work is now completed, Pocklington Steel have done an excellent job.
65% of the roof is on and completion will be next Wednesday (unless we have more rain as we did yesterday!)
Wall panels have commenced; floor preparation is ongoing as internal drainage draws to an end, completion of the concrete to the floor slab will be on Friday 14th August.
A water attenuation lagoon has been made and external drainage is to start on Monday 10th August.