Contract Managers Progress Report


The shell is now complete, and we have started on the dock levellers. External groundworks are arounf 80% completed. Inside the building the insulated walls are also around 80% completed. Mechanical and electrical works are 40% complete. Underfloor heating works started today. The first fix of the sprinkler system is underway. This work is being carried out by Hall and Kay