Steelwork now almost complete, roof works commencing, also fire protection (employing Demon)
Pages
Tuesday, 30 June 2009
Site manager's report
Steelwork now almost complete, roof works commencing, also fire protection (employing Demon)
Foundations are complete, and we are installing the pre-cast concrete floor at mezzanine level
Monday, 15 June 2009
Site Managers Weekly Report
All is currently progressing well on site, with 50% of the structural steelwork now completed. We are using Pocklington Steel, who have performed excellently so far. Masonry work started last Wednesday, with Duncan and Malcolm from Squareline doing their usual good work. Contrac Cladding are due to start the roof works on Monday. Foundation works are 80% completed. Jelle from J Z Flowers visited the site on Saturday and was impressed at how smoothly the works are progressing.
Dave Taylor
Labels:
Site Managers Report
Friday, 12 June 2009
Tuesday, 9 June 2009
Site Contacts
Contract Number: H8422
Site Name: J Z Flowers
Site Agent: Dave Taylor
E-mail: dave.taylor@hobson-porter.co.uk
Site Address:
Mobile Number: 07870 277910
Labels:
Contact
Subscribe to:
Posts (Atom)