The shell is now complete, and we have started on the dock levellers. External groundworks are arounf 80% completed. Inside the building the insulated walls are also around 80% completed. Mechanical and electrical works are 40% complete. Underfloor heating works started today. The first fix of the sprinkler system is underway. This work is being carried out by Hall and Kay
Pages
Showing posts with label Hall and Kay. Show all posts
Showing posts with label Hall and Kay. Show all posts
Monday, 5 October 2009
Contract Managers Progress Report
The shell is now complete, and we have started on the dock levellers. External groundworks are arounf 80% completed. Inside the building the insulated walls are also around 80% completed. Mechanical and electrical works are 40% complete. Underfloor heating works started today. The first fix of the sprinkler system is underway. This work is being carried out by Hall and Kay
Labels:
groundworks,
Hall and Kay,
shell,
underfloor heating